June 15, 2007, Underwood Plaza Update
Structural steel erection commenced on Monday, 06/11/07, and by week’s end the majority of the first lift of columns and most of the Second Floor Level beams at the north half of the building had been installed.
Formwork was removed from the north and east foundation walls and the central staircase walls.
Waterproofing was applied to the west foundation wall, and backfilling with drainage rock was started.




























Formwork was removed from the north and east foundation walls and the central staircase walls.
Waterproofing was applied to the west foundation wall, and backfilling with drainage rock was started.