August 19, 2007, Underwood Plaza Update
Fayetteville Mechanical continued running copper HVAC piping over the 1st and 2nd Floor Levels and was having drain pipe floor penetrations core drilled on the 3rd Floor Level. Cast iron drain piping was also being hung below the 2nd Floor Level.
Crossland Steel continued setting bar joists at the 4th Floor Level, along with bridging, balcony framing and angles at framed openings, and continued setting diagonal bracing between the 3rd and 4th Floor Levels.
Welding of the column splices just above the 3rd Floor Level continued. By week's end, floor decking was being laid at the 4th Floor Level.
Max True Fireproofing continued spraying steel below the 2nd Floor Level and began spraying steel below the 3rd Floor Level.
Crossland Concrete fine graded gravel, set slab edge forms and laid down plastic sheeting and wire mesh at the 1st Floor Level. Major portions of the 1st Floor slab were poured.




















































Crossland Steel continued setting bar joists at the 4th Floor Level, along with bridging, balcony framing and angles at framed openings, and continued setting diagonal bracing between the 3rd and 4th Floor Levels.
Welding of the column splices just above the 3rd Floor Level continued. By week's end, floor decking was being laid at the 4th Floor Level.
Max True Fireproofing continued spraying steel below the 2nd Floor Level and began spraying steel below the 3rd Floor Level.
Crossland Concrete fine graded gravel, set slab edge forms and laid down plastic sheeting and wire mesh at the 1st Floor Level. Major portions of the 1st Floor slab were poured.