Fayetteville Mechanical continued running copper HVAC piping and PVC piping over the 1st Floor, installed steel HVAC riser piping with run-outs at the 2nd Floor Mechanical Room, continued welding up steel HVAC piping for installation over the 2nd Floor, continued installing PVC risers in the Mechanical Room up through the 4th Floor, began installing gas piping at the 2nd Floor entry point, core drilled pipe penetrations at the 4th Floor slab and was running steel HVAC branch lines over the 2nd Floor.
Midwest Drywall installed drywall at the partition wall in the 1st Floor Mechanical Room, received metal studs in preparation for installation at the 2nd Floor exterior and continued laying out walls on the 2nd and 3rd Floors.
Crossland Steel installed steel posts and beams to support the stair entering the building at the northeast corner from Dickson Street to the 1st Floor, completed installation of bar joists at the 5th Floor and installed bridging, installed perimeter angle and angles at framed openings at the 5th Floor and began setting floor decking up on the 5th Floor.
Crossland Concrete removed forms from the concrete bases at the loggia columns at the 1st Floor, dressed up the concrete walls at the central staircase, installed rock base for the grade beams at Powerhouse Row and poured concrete at the south stair from the 2nd to 3rd Floor and at miscellaneous slab blockouts.
Bill’s Electric continued receiving electrical panels and equipment on site and set several panel boxes in the 1st Floor Mechanical room.
Max True Fireproofing installed lath at bar joists over the 3rd Floor.
Walker Masonry erected the 3 brick sample panels.






























Midwest Drywall installed drywall at the partition wall in the 1st Floor Mechanical Room, received metal studs in preparation for installation at the 2nd Floor exterior and continued laying out walls on the 2nd and 3rd Floors.
Crossland Steel installed steel posts and beams to support the stair entering the building at the northeast corner from Dickson Street to the 1st Floor, completed installation of bar joists at the 5th Floor and installed bridging, installed perimeter angle and angles at framed openings at the 5th Floor and began setting floor decking up on the 5th Floor.
Crossland Concrete removed forms from the concrete bases at the loggia columns at the 1st Floor, dressed up the concrete walls at the central staircase, installed rock base for the grade beams at Powerhouse Row and poured concrete at the south stair from the 2nd to 3rd Floor and at miscellaneous slab blockouts.
Bill’s Electric continued receiving electrical panels and equipment on site and set several panel boxes in the 1st Floor Mechanical room.
Max True Fireproofing installed lath at bar joists over the 3rd Floor.
Walker Masonry erected the 3 brick sample panels.