November 30, 2007, Underwood Plaza Update
Interior partitions began being framed up at the 2nd Floor Level.
Slab edge angle was being installed at the 9th Floor Level. Metal decking and reinforcing mesh was installed for the 9th Floor slab. Floor drains, blockouts and sleeves were installed in preparation for the 9th Floor slab pour the coming week.
Sheathing board and framing for brick pilasters was being installed at the north elevation from a swinging stage. Interior partition walls were being framed up at the 7th Floor Level.
The fire pump was delivered to the site.
The electrical subcontractor continued running MC cable risers.
The elevator control gear was placed on the 8th Floor Level.
Brick and cast stone for the west elevation was delivered to the site. The mason mobilized, and his mortar silo was brought on site.
























Slab edge angle was being installed at the 9th Floor Level. Metal decking and reinforcing mesh was installed for the 9th Floor slab. Floor drains, blockouts and sleeves were installed in preparation for the 9th Floor slab pour the coming week.
Sheathing board and framing for brick pilasters was being installed at the north elevation from a swinging stage. Interior partition walls were being framed up at the 7th Floor Level.
The fire pump was delivered to the site.
The electrical subcontractor continued running MC cable risers.
The elevator control gear was placed on the 8th Floor Level.
Brick and cast stone for the west elevation was delivered to the site. The mason mobilized, and his mortar silo was brought on site.