November 16, 2007, Underwood Plaza Update
Slab edge formwork continued to be erected at the southeast wing of the main building and drainage rock continued to be placed.
Exterior metal studs continued to be installed at the 6th Floor Level, now at the east elevation.
Metal studs and sheathing board for the brick pilaster columns were being installed at the west elevation.
Columns above the 8th Floor splice point continued to be stood up and welded into place. Beams for the 9th Floor Level continued to be hung.
Diagonal bracing in conflict with corridor doors were relocated.
Metal grating at the north chase continued to be installed.
Wood blocking at exterior door and window openings continued to be installed.












Exterior metal studs continued to be installed at the 6th Floor Level, now at the east elevation.
Metal studs and sheathing board for the brick pilaster columns were being installed at the west elevation.
Columns above the 8th Floor splice point continued to be stood up and welded into place. Beams for the 9th Floor Level continued to be hung.
Diagonal bracing in conflict with corridor doors were relocated.
Metal grating at the north chase continued to be installed.
Wood blocking at exterior door and window openings continued to be installed.