March 7, 2008, Underwood Plaza Update
Excavation took place for the grade beam along the south side of the Parking Deck.
Reinforcing steel cages for the piers at the Parking Deck continued to be brought on site.
Copper water piping continued to be run throughout the building.
Fire sprinkler standpipes for hose stations were run at the two main staircases.
The mason continued setting miscellaneous cast stone pieces at the West Elevation.














Reinforcing steel cages for the piers at the Parking Deck continued to be brought on site.
Copper water piping continued to be run throughout the building.
Fire sprinkler standpipes for hose stations were run at the two main staircases.
The mason continued setting miscellaneous cast stone pieces at the West Elevation.