February 9, 2008, Underwood Plaza Update
Exterior sheathing board continued to be applied at the East Elevation.
Framing of the parapet and installation of plywood sheathing and wood blocking continued at the roof
Drains were installed at the main roof in preparation for the roofer starting.
Brick support relief angles were being installed at the 5th Floor Level at the West Elevation. The mason installed through wall flashing along the top of the angles and continued laying brick from the 5th Floor Level up.
Plywood floor decking was installed at the corridor ramp on the 2nd Floor.
Plumbing rough in continued at the upper floors.
Site excavation and grading commenced at the west end of the parking deck area.
Exterior wood doors and windows were being installed at the North Elevation.
Shaft wall framing and liner panels were being installed at the elevator hoist-way and at the north staircase.


























Framing of the parapet and installation of plywood sheathing and wood blocking continued at the roof
Drains were installed at the main roof in preparation for the roofer starting.
Brick support relief angles were being installed at the 5th Floor Level at the West Elevation. The mason installed through wall flashing along the top of the angles and continued laying brick from the 5th Floor Level up.
Plywood floor decking was installed at the corridor ramp on the 2nd Floor.
Plumbing rough in continued at the upper floors.
Site excavation and grading commenced at the west end of the parking deck area.
Exterior wood doors and windows were being installed at the North Elevation.
Shaft wall framing and liner panels were being installed at the elevator hoist-way and at the north staircase.